The Telford Bridge (Updated)

The Telford Bridge

The replacement works are running ahead of schedule so the timetable has been brought forward.

Outline of the timeline and key information:

  • Thursday 27th February 2025 - Temporary bridge removal

  • Saturday 1st March 2025 – Refurbished bridge to be delivered and placed into the pits

  • Mid-March 2025 All final connections and testing to be completed (expected to take approximately 14 days to be completed – but working to shorten this if at all possible)

  • w/c 17th March 2025 - Final Commissioning and Telford Bridge fully operational