The Telford Bridge (Updated)
The Telford Bridge
The replacement works are running ahead of schedule so the timetable has been brought forward.
Outline of the timeline and key information:
Thursday 27th February 2025 - Temporary bridge removal
Saturday 1st March 2025 – Refurbished bridge to be delivered and placed into the pits
Mid-March 2025 – All final connections and testing to be completed (expected to take approximately 14 days to be completed – but working to shorten this if at all possible)
w/c 17th March 2025 - Final Commissioning and Telford Bridge fully operational